Keith Boden Wetlands Desilting Continues as Part of Staged Rehabilitation

Desilting works at Keith Boden Wetlands in Wavell Heights are continuing as part of a staged program to improve the site’s stormwater treatment function. The project focuses on removing sediment that has accumulated over many years and has affected how effectively the wetland operates.



The current works form one part of a broader approach to maintaining and improving the site. Council’s published timeframe scheduled the project for completion by July 2026, but its webpage still listed the works as in progress as of early August.

The remaining project scope includes sediment disposal, minor edge stabilisation, removal of temporary works and the gradual restoration of water levels.

Sediment Removal Supports the Wetland’s Original Purpose

Keith Boden Wetlands was constructed at Shaw Park in 1998 to filter sediment and pollutants from stormwater before it enters Kedron Brook and, further downstream, Moreton Bay. As the wetland captures material from the surrounding catchment, sediment naturally collects within the system.

Over time, that build-up can reduce the wetland’s ability to function effectively. The current desilting work aims to remove accumulated material and improve the system’s performance.

Funding for the rehabilitation was secured for the 2025–26 financial year. Northgate Ward Cr Adam Allan advised residents in April that works were expected to begin on 25 May, subject to weather and final scheduling.

Photo Credit: Clax Saxon/Facebook

Council now describes the current phase specifically as desilting. The sediment removal forms part of a staged approach, while planning for future rehabilitation continues.

Specialised Work Within the Wetland

The project uses specialised equipment within the wetland, while access through the surrounding park is maintained where possible. A temporary track forms part of the works and provides access for construction vehicles and machinery.

The project also includes a contained work area within the wetland to manage water levels safely during sediment removal. Earlier information outlined plans to use a floating excavator within this section.

Workers will dewater the removed material before transporting it to a licensed disposal facility. The scope also includes minor stabilisation along sections of the wetland edge.

After the desilting work, crews will remove temporary infrastructure and allow rainfall to restore normal water levels gradually. These final steps form part of returning the site to its usual operating condition.

Temporary Changes Remain Around Shaw Park

Residents and park users may continue to see machinery around Keith Boden Wetlands while the project remains underway. Pumps may create daytime noise, while disturbed sediment can produce temporary odours.

Water levels may also remain lower during the works and for a short period afterwards. These temporary changes should ease once the project finishes and rainfall gradually restores normal conditions.

Access through Shaw Park will be maintained where possible during construction. Traffic control and detours will help keep pedestrians and cyclists clear of active work areas.



The project’s central purpose remains to improve the wetland’s ability to intercept sediment and other pollutants before stormwater reaches Kedron Brook and Moreton Bay. The current desilting phase addresses the immediate build-up while longer-term rehabilitation planning continues.

Published 4-Aug-2026

Keith Boden Wetlands Rehabilitation: Start Date Confirmed and Here’s What’s Planned

Rehabilitation works at the Keith Boden Wetlands at Shaw Park are set to commence on 25 May, subject to final scheduling and weather conditions.


Read: Keith Boden Wetlands Restoration Gains Momentum


The news came via an April 24 community update from Cr Adam Allan, who confirmed that Council officers have provided advice that the project is set to get underway next month.

“Thank you to the community for your patience and understanding while these complex works have been planned,” Cr Allan wrote in his Facebook post. “This is a surprisingly complicated project which entailed detailed design and bespoke project methodology in order to progress the project.”

A Wetland With a Long History and a Growing Problem

Photo credit: Google Maps/Caro Sierra

The Keith Boden Wetlands were originally constructed in 1998 with a clear environmental purpose: to filter sediment and pollutants from stormwater runoff before it flows into Kedron Brook and eventually Moreton Bay. After 25 years, accumulated sediment has taken a toll on the wetlands’ ability to function effectively.

Excessive sediment build-up has led to exposed mudbanks and decaying organic matter that have worsened despite recent rainfall events, degrading both water quality and local biodiversity in the process. As Cr Allan put it in his funding announcement, the wetlands are in need of TLC to keep working effectively.

Funding to carry out the rehabilitation was secured for the 2025-2026 financial year.

What the Works Will Involve

Photo credit: Google Maps/James Gibson

What can residents and park-goers expect once works begin? According to Cr Allan’s update, the project involves several stages of construction activity.

A temporary access track will first be built to allow construction vehicles to safely reach the site. Temporary detours and traffic control measures will also be put in place to protect pedestrians and cyclists using the area during the works.

The centrepiece of the project is the deployment of a floating excavator, which will work within a temporary bunded area inside the wetland. The excavator will remove the years of built-up sediment that has accumulated on the wetland floor. That material will be dewatered on-site before being transported off to a licensed facility, a requirement under the permits issued for the project.

Minor repairs to some of the retaining walls along the wetland’s edge are also planned as part of the scope of works.

Project signage with information and contact details will be installed on-site, so residents visiting Shaw Park will be able to stay informed as works progress.


Read: Community Calls for Action as Wavell Heights Wetlands Decline


A Complex Project With a Lot of Moving Parts

Cr Allan was candid about why it has taken time to get to this point. The project required detailed design work, a bespoke methodology, and a range of approvals and permits from the State Government, along with significant dialogue with State agencies to ensure the works could be completed safely and responsibly.

Cr Allan acknowledged the community’s patience throughout this process. Restoring the wetlands’ capacity to filter stormwater will benefit not only Shaw Park but the broader Kedron Brook catchment and Moreton Bay downstream.

Published 4-May-2026